Forsyth & N. Meramec Resurfacing Project Begins June 13

There will be road closures due to crosswalk and curb ramp reconstruction and resurfacing on Forsyth and N. Meramec.  Throughout this project, updated information and maps will be available on the project page.  

Work on curb ramps and crosswalks in the downtown area of Forsyth will continue through the second week of July.  After that, work will begin on N. Meramec and last through the end of July.  Work on N. Forsyth will take place in August.  Milling and paving will begin the second week of August.