The City of Clayton is a high quality residential and business community. Please be courteous to neighboring residents and ensure your job site is clean and gates are secure when contractors are not on site. Thank you for your cooperation. Failure to comply with these regulations can result in the issuance of a Stop Work Order and/or legal action which could result in court imposed fines.
Construction Hours
Construction is permitted Monday through Friday - 7:00a.m. to 6:00p.m.
No work is to be done on Saturdays, Sundays, evenings or holidays without an Emergency/Evening/Weekend Work Permit. Applications for after hours work are reviewed and issued by the Public Works Department and may be obtained by calling 314-290-8540 or printed from the Applications, Forms, and Permits webpage.
Neighboring Property and Access
There must be no trespassing onto neighboring properties either by workers or equipment. Litter must be promptly and properly disposed of and must not be present on neighboring properties at any time. Mud on the sidewalk and street must be cleaned constantly. Neighboring driveways are not to be blocked by equipment or construction parking.
Job Site Management
Construction equipment including trailers, portable toilets, construction materials and dumpsters are not to be stored in the front yard areas without City approval. Dumpsters not behind a construction fence will require a Dumpster Permit. Dumpsters are required to be covered to minimize littering of debris on adjacent properties. All mud or debris must be continually removed from the public sidewalks and streets. Straw bales must be provided when necessary to prevent mud runoff to adjacent properties and public right-of-ways. If the project requires a construction fence to be erected, the regulations listed below must be followed. All weeds and grass need to be maintained not to exceed a 6 inch maximum at all times. The job site must have all permits posted in public view. The approved permit plans are to remain on the job site at all times during construction.
Construction Fences
No construction fences may be erected until the Building Official approves a site plan depicting the materials, location and access gates. All buildings undergoing construction, substantial rehabilitation, removal, demolition or any and all excavations exceeding 5 feet in depth (except sewer and utility trenches) shall be enclosed on all sides with a solid wood construction fence not less than 6 feet in height. All construction fences and gates must be secure when contractors are not on site!
Duration and Removal of Temporary Construction Fences: Construction fences may not be erected more than 10 calendar days prior to demolition or the commencement of construction and must be approved by the Building Official prior to the construction of the fence. If demolition or construction does not commence within 10 days of installation, the fence must be removed and the site restored.
Construction Parking
All construction projects with a value of $2,500,000 or greater are required to follow an approved Construction Parking Management Plan to identify how construction parking will be facilitated and regulated to prevent conflicts and issues on public streets and surrounding property. In addition, projects valued under $2,500,000 may also be required by the Building Official to have an approved CPMP. The determination will be based on the existing parking conditions in the impacted area. The CPMP is to be submitted as part of the application for a Building Permit or Demolition Permit.
Right-of-Way
Prior to any excavations on public right-of-way or tree lawn areas, a Right-of-Way Permit is required and can be obtained from the Public Works Department (314-290-8540). Curb cuts, public driveway approaches and public sidewalks are projects that require Public Works approval.
Existing sidewalks must be maintained throughout the construction process. Construction related damage will require the replacement of damaged sidewalks to the specifications of the Public Works Department.
In situations where the Public Works Department has approved construction fences encroaching upon the public right-of-way, such fences will require a temporary sidewalk be constructed and maintained, extending no more than 4 1/2 feet beyond the curb line. Such walks shall be no less than 4 feet in width, constructed in a safe and substantial manner and provided with a roof and handrails as deemed necessary by the Building Official. The Building Official may require the sidewalk be properly lighted as a protection to the public from effects of construction or demolition.
Signs
Temporary signs may be erected in conformance with Section 425.070 of the City’s Code of Ordinances. Sign types are regulated based on the property zoning (residential or non-residential), location and size.
Tree Protection and Stormwater Pollution Protection Measures
Any construction, demolition, site work or similar activity which may injure existing trees requires the implementation of tree protection measures as set forth in the regulations or as determined by the City’s contracted landscape architect. Tree protection measures shall remain in place throughout construction.
Projects with a disturbance area requiring a Site Plan Review Permit or a Land Disturbance Permit shall be managed in accordance with the permit requirements. All other projects shall be responsible for managing mud, dirt, silt or similar created by construction activities to prevent such from ponding on public right-of-way or adjacent properties.