Brentwood Blvd. Resurfacing

Print
Press Enter to show all options, press Tab go to next option

Summary

The City of Clayton has received federal funding for a preservation project to resurface Brentwood Blvd. from Forsyth to Clayton.  This federal funding application included resurfacing of the roadway, upgrading curb ramps to ADA standards, brick paver crosswalks, and a landscaped median (Bonhomme to Shaw Park).

Schedule

Easement acquisition is now complete and final plans have been approved by MoDOT.  We are awaiting authority to advertise from FHWA and the project will be put out to bid as soon as possible (July/August of 2019).  We will work with the selected contractor as much as possible to complete this project this calendar year, but the extended time required to secure the necessary easements may result schedule delays (weather dependent).

Design

December 2018 - Final plans are under review and easement acquisition is near complete.  Pending MoDOT approval of plans, the project is planned to be bid this winter with construction starting in the spring/summer and lasting approx. 3 months. 

June 5, 2018 - Property negotiations for easements/row are finalizing and final plans will be submitted to MoDOT this month.  Link below to the plan sheets showing the project extents.

BrentwoodPlan Sheets

 January 23, 2018 - Right of way plans have been approved by MoDOT and final plans are underway.  The City will soon be contacting property owners along the route for which easement or right of way is needed.

 April 18, 2017 - Public Works staff, and the project design consultants, presented to the Board of Alderman on the Brentwood Blvd. Resurfacing Project.  Staff provided an update on the design evolution and after thorough discussion, it was determined that the project would proceed as initially programmed and a short median being added just north of Shaw Park Drive but stopping short of the existing driveways.  The median will be approximately 60' long and provide refuge for pedestrians crossing Brentwood east/west at this location.  Staff will be evaluating future opportunities for bicycle/pedestrian access along Brentwood.

March 14, 2017 - Public Works and HR Green presented the original option, plus four additional options, to the Board of Alderman for comparison and consideration.  The presentation materials can be viewed at the link below.

Brentwood Blvd. Update to BOA (3/14/17)

December 7, 2016 - City hosted an Open House to present the project to the public and receive feedback prior to design.  A number of items were raised, including medians,  pedestrian facilities, and two-way bicycle facilities. 

Following the Open House, Public Works provided a project update to the Board of Alderman in late December which included feedback received from the Open House.  From this meeting Public Works Staff worked with HR Green, a third-party design engineer, and CBB, a third-party traffic engineer, to develop and evaluate options to address comments received at the Open House.

Map:

 Brentwood Blvd Resurfacing

Contact:

Matt Malick, P.E.
Assistant Director of Public Works
(314) 290-8547
mmalick@claytonmo.gov