Home MenuCentral Business District Resurfacing
Summary
The City of Clayton has received federal grant funding for the Central Business District (CBD) Resurfacing Project to mill and overlay the streets in the downtown area. This project will also address non-compliant ADA curb ramps and install brick paver crosswalks to replace stamped asphalt crosswalks. The project consists of two phases. Phase 1 was completed in the Spring of 2025, with construction on phase 2 having begun in February of 2026.
Phase 2
The City awarded the contract for Phase 2 (which includes North Brentwood Boulevard between Maryland Avenue and Forsyth Blvd., Carondelet Avenue west of Hanley Road, as well as Central and Bemiston Avenues between Maryland Avenue and Forest Park Parkway) to Byrne & Jones Construction in June 2025. Construction is expected to begin the week of February 2nd on Carondelet Avenue, with work to include concrete curbs, sidewalks, ADA ramps, and roadway base repairs. Milling and paving operations will follow shortly thereafter.
Construction work is weather dependent, so the schedule is subject to change. Any changes to the project schedule will be posted here, so please continue to check this site for the latest updates and specific street closures for each weekend.
This website will be the primary source for up to date information throughout the design and construction of the project. As updates are available (particularly during construction), they will be posted on this page. The short URL for future access is www.claytonmo.gov/cbdresurfacing.
| Task | Expected Start Date* | Duration |
| Carondelet Ave (Brentwood to Meramec) - Concrete Replacements | February 2nd | 1 Week |
| Carondelet Ave (Central to Hanley) - Concrete Replacements | February 9th | 1 Week |
| Central Ave (Shaw Park Dr. to Maryland) - Concrete Replacements | February 16th | 2 Weeks |
| Bemiston Ave. (Shaw Park Dr. to Maryland) - Concrete Replacements | February 23rd | 2 Weeks |
| 10 block of N. Brentwood Blvd. - Concrete Replacements | February 23rd | 3-4 Weeks |
| All Streets - Paving Operations |
To Be Determined |
TBD |
*start dates and duration are estimates and subject to weather/work delays
Overall Project Area - Phase 2
Contact
Rich Wilburn, PE
(314) 290-8565
rwilburn@claytonmo.gov